Tenerife moves to reject Underwater Gardens project
The Cabildo de Tenerife has approved this Friday a proposal to submit to the island’s full council the denial of approval for the Underwater Gardens Project of Insular Interest, on the grounds that it “fails to meet the environmental, technical, territorial and economic requirements” for approval. The infrastructure was planned for Punta Blanca in Guía de Isora, right on the protected marine strip of Teno-Rasca.
“Our obligation is to defend the general interest of the island, protect the territory and ensure that any initiative developed in Tenerife lives up to the demands,” the island president told the media at the press conference following the agreements of the island government council.
A long-running battle over the project
Dávila recalled that in June 2026 the Cabildo first set out its “unfavourable” position on an initiative that had been recognised by the previous island government, led by Pedro Martín (PSOE), as a Project of Insular Interest, and which had lost its stated aim of “environmental regeneration”. Once that decision was taken by the Tenerife Cabildo, the promoter submitted its objections in July 2026. However, after studying its arguments, the island authority considered that the latest proposal “departs” from the initial project presented and declared in 2022 as a Project of Insular Interest — a recognition which, Dávila stressed, “never meant automatic authorisation or a blank cheque”.
“We have given the company the opportunity, through objections, to supplement its documentation, however, the technical and legal reports are conclusive: the deficiencies (of the project) remain unresolved. Our obligation is to defend the general interest of the island, protect the territory and ensure that any initiative developed on the island of Tenerife lives up to the demands,” she added.
Failings identified by the Cabildo
Dávila said that the infrastructure, planned on rustic land under coastal environmental protection, is also not justified as “an essential infrastructure” for the island, nor are the availability of land, the estimated execution costs, or the financing and environmental protection guarantees required.
Last June, the Cabildo de Tenerife announced the halting of the project, which was to occupy 10.6 hectares of rustic land on the coast of Guía de Isora. It did so four years after declaring it of insular interest, until it brought it down — driven not only by the disappearance of the reasons that underpinned that declaration, but also by the social and environmental campaign the park had faced since the project came to light.
Opposition from ecologist groups
The scheme met with rejection from various groups from the outset. The Salvar Punta Blanca platform, Greenpeace and Ecologistas en Acción warned that it was a clear example of greenwashing which, far from regenerating the area, would represent one more threat. On 30 April, Salvar Punta Blanca demanded that the current president of the Cabildo, Rosa Dávila (CC), withdraw the declaration of insular interest granted to Underwater Gardens.
Ecologistas en Acción maintains that a regenerative park should involve “minimal and respectful intervention”, and not a tourist complex attracting thousands of people every day. The project documentation spoke of around 3,000 visitors a day. Along these lines, the Tenerife Association of Friends of Nature (ATAN) insisted that the scheme would not generate positive environmental effects, but rather an “irreversible loss of land”, an increase in polluting water discharges and greater pressure on the area.
Claims of a “double game” over WaveGarden
Following the announcement of the halting of Underwater Gardens, Canarias Tiene un Límite criticised Rosa Dávila’s “double game”. The platform has claimed that while the president of the Cabildo brings down the insular interest of one project, she has on the table a “new threat” for the coastline of the south of the island. Specifically, Canarias Tiene un Límite claims that an artificial wave theme park known as WaveGarden is planned opposite La Tejita beach and on agricultural land. The Cabildo denies this.
Canarias Tiene un Límite said in a statement that several of the WaveGarden projects have been cancelled or rejected in other parts of Spain, such as Donostia and Barcelona. “We demand the immediate denial of any figure of insular interest or administrative authorisation for WaveGarden and we call, once again, for a real tourism moratorium that halts the construction of hotels, beds and infrastructure such as this on the Canary Islands coastline,” they stress.
What’s happening in the Canaries – straight to your phone