Almost five years without parking in the heart of Puerto de la Cruz
The Plaza de Europa car park in the heart of Puerto de la Cruz is expected to reopen in mid-to-late 2028, by which time it will have been closed for almost five years, having shut at the start of 2024. The revival of this infrastructure, seen as essential to easing parking problems in the town centre, is now beginning to take shape with the approval of an agreement between the Cabildo de Tenerife and Puerto de la Cruz town hall under the island’s Tourism Product Improvement Programme, which will release 5.3 million euros to repair its structural deficiencies and renew its facilities.
A fully funded deal with no cost to the town hall
In the words of the mayor of Puerto de la Cruz, Leopoldo Afonso, the agreement represents “an important step towards recovering a car park that is necessary for mobility and commercial activity in the centre”, one that will benefit residents and workers as well as visitors to the town. What is more, the island authority will cover the investment in full, with the town hall not having to contribute a single euro, and the funding will be spread across the 2027 and 2028 financial years, with a further commitment to absorb any cost overruns that may arise during the works.
The municipal contribution will therefore be limited to temporarily making available the land needed to carry out the work and giving its approval to the tender procedures, under an agreement that will run for four years. The funding also honours a commitment set out in the coalition agreement signed in 2024, as recalled by the councillor for Sustainable City and Urban Agenda, David Hernández. He highlighted the work carried out by the urban planning department to drive forward an intervention whose first steps date back to 2021, when the town hall — then under PSOE control — commissioned the drafting of a project that has now been updated by the architect José Moriana Pericet, of the construction firm Cemosa, and whose tender is expected to be approved, according to the Cabildo’s forecasts, at the end of December.
Eighteen months of works to restore more than 300 spaces
From that point, the successful contractor will have 18 months — four more than initially approved by the island’s governing council on 7 October — to carry out the works and return the more than 300 parking spaces to public use. According to the vice-president and island councillor for tourism, Lope Afonso, the works involve “various structural and technical interventions” in an infrastructure that is key to mobility in the town centre. Among the planned actions, he continued, “are the repair of the structural defects detected, waterproofing work and the renewal of the fire protection, ventilation and electrical systems, as well as improvements to accessibility within the complex”.
Safety defects forced the initial closure
The closure of the car park, initially decreed on a temporary basis on 15 March 2024, was prompted by deficiencies detected in the fire protection and smoke extraction systems. The town hall, then led by the PSOE, went as far as proposing a gradual reopening in the following weeks, a forecast that never materialised. These problems were compounded by structural defects in the floor slab, persistent leaks and falling materials, particularly from the ceiling, all of which laid bare the deterioration of the infrastructure.
A landmark with a place in the town’s recent history
The complex forms part of the recent history of Puerto de la Cruz. Inaugurated in 1992, the Plaza de Europa was designed by the La Orotava-born architect Luis García Mesa on land formerly occupied by a municipal livestock market and a defensive battery. Covering some 5,000 square metres, the space — conceived as an open fortress facing the Atlantic and presided over by six 18th and 19th-century cannons — houses two floors of parking beneath its structure that served the heart of the town for more than three decades.
Its recovery will now form part of the transformation the historic centre of Puerto de la Cruz has undergone in recent years, with works on the Paseo de San Telmo, Calle San Juan, the Plaza Concejil and Calle Iriarte and Calle Quintana. Through this intervention the Cabildo aims to complete the rehabilitation of the area, restoring to the town centre an infrastructure that is fundamental to its mobility and commercial activity.